Wave Hosting Santa Clara

Wave Hosting Santa Clara Data Center, USA

  • Wave Hosting Santa Clara

15,000 Sq. Ft. ready available, 150 wpsf, up to 20kW per cabinet, carrier neutral. 100Gbps MPLS network interconnected with all major datacenters and network providers.

Power
Eaton and Russelectric switch gear
3 Powerware 9315, 500KVA UPS Modules in N+1 configuration
2 Cummings 1850KVA Diesel Generators
11000 Gallons of Fuel on Site
24 Hour on call Refuel Contract from multiple vendors

Environmental Controls
Leibert 30 ton CRAC units with N+1 Redundancy
Automated Logic Building Management System

Security
Manned 24x7x365
Access to the facility and colocation floor is controlled by biometric palm scanners.
All cabinets and cage spaces use individual keys.
Facilities are monitored via closed circuit digital camera coverage with 24 hour recording and 120 day digital video storage.
24 Hour Critical Systems Monitoring/Disaster Prevention
All systems (including UPS, DC Power, PDU, HVAC, Temperature, Humidity, Security, Fire Threat) are constantly checked by monitoring systems.
Fire detection is managed with a VESDA air sampling system as well as smoke and heat detection sensors.
Fire Suppression: FM200 and Dry-pipe pre-action

IEM Switchgear
4 Powerware 9315, 500KVA UPS Modules in N+1 configuration
2MW Caterpillar Generator
On Call Refueling Contract from multiple vendors
AC and DC power is available.
Environmental Controls
Data Aire HVAC system
3 Carrier 150 Ton Chillers
4 Cooling Zones
There is constant ambient air temperature of 75 (+ or - 2 degrees).
Humidity is controlled to a constant 45% (+ or - 5 %).
All cooling systems are fully N+1 Redundant
Security
Manned 24x7x365
Access to the facility and colocation floor is controlled by biometric palm scanners.
All cabinets and cage spaces use individual keys.
Facilities are monitored via closed circuit digital camera coverage with 24 hour recording and 120 day digital video storage.
24 Hour Critical Systems Monitoring/Disaster Prevention
All systems (including UPS, DC Power, PDU, HVAC, Temperature, Humidity, Security, Fire Threat) are constantly checked by monitoring systems.
Fire detection is managed with a VESDA air sampling system and Laser grid smoke detectors.
Dry-pipe pre-action systems complement the front-line detection system.